On December 16, 2022 the Oregon Public Utility Commission (Commission) approved PacifiCorp’s request for a general rate revision. The Oregon Commission approved a revenue requirement of approximately $51.4 million, representing a 3.9% increase from its previous rates. The Commission also approved new rates for the Power Cost Adjustment Mechanism (PCAM) and the Transition Adjustment Mechanism (TAM), and later in the proceeding approved a new green tariff for PacifiCorp. [Read more…]
Oregon Commission Issues Order in Docket No. UM 2032 Related to Network Upgrade Cost Allocation and Interconnection Service for QFs
On January 20, 2023, the Oregon Public Utility Commission (Commission) released an order in Docket No. UM 2032 related to network upgrade cost allocation and interconnection service for qualifying facilities (QFs). The Commission directed Commission Staff to open an informal rulemaking related to state-jurisdictional transmission planning. The Commission also directed the utilities to accept an interconnection service besides Network Resource Integration Service (NRIS) if the QF will negotiate a non-standard contract and consent to curtailment. [Read more…]
Oregon Court of Appeals Affirms Oregon Public Utility Commission Order Regarding PGE’s PURPA Fixed Price Term and Oregon Public Utility Commission Jurisdiction
On January 5, 2023, the Oregon Court of Appeals affirmed an appeal of the Oregon Public Utility Commission’s (Commission) order in Docket No. UM 1931 regarding Commission jurisdiction over executed Public Utility Regulatory Policies Act (PURPA) contracts and the start of Portland General Electric Company’s (PGE) fixed-price term under then-existing standard power purchase agreements (PPA). The Court’s decision held that the 15-year fixed-price period under PGE’s then-existing PURPA PPAs began at contract execution not commercial operation date and that the Commission has jurisdiction over executed contracts between qualifying facilities (QFs) and the utilities. [Read more…]
Oregon Commission Acknowledges Idaho Power’s 2021 IRP
On December 30, 2021, Idaho Power filed its 2021 Integrated Resource Plan (IRP) with the Oregon Public Utility Commission (Commission). The Commission acknowledged the 2021 IRP and adopted Commission Staff’s recommendations at a public meeting on December 6, 2022 and memorialized that decision in an order on January 13, 2023. [Read more…]
OPUC Prohibits the Use of the “Agent Subscription Model” in Oregon’s Community Solar Program
On October 6, 2022, the Oregon Public Utility Commission (the Commission) issued an order prohibiting the use of the “agent subscription model” in the Oregon Community Solar Program (CSP). [Read more…]