The Montana Supreme Court Rules Against the Montana Commission’s Approval of Shorter Contract Terms and Lower Avoided Cost Prices

On August 24, 2020, the Montana Supreme Court ruled against the Montana Public Service Commission’s (Montana Commission) actions to reduce avoided cost rates and shorten contract terms for power purchase agreements between the utilities and solar Qualifying Facilities (QFs). The ruling is a victory for renewable energy developers and advocates, as it upheld an integral piece of the Public Utility Regulatory Policy Act of 1978’s (PURPA) that encourages QF development. [Read more…]